ABSTRACT
The network modellling (CPM and PERT) was used to profer
a solution to the problem of inadequate portable water in rural communities in
the thirty-one Local Government Areas of Akwa Ibom State, time estimates were
the materials used to analyzed the duration of the project. The summarized
result in Table 4.4 gave the optimal duration in hours: 26.92 for site
preparation/mobilixation of geophysical surveying team, selection/analysis
involved in the best water yielding point was 37.72 for conveying drilling team
to the site, 168 for installation of submersible pump, 4.3 gravel
packing/casting of the well platform, 1.2 for flusing water analysis was 26.92
while 78.04 was for commisioing of the project. Network analysis techniques was
used to determine the normal duration of executing a submersible pump for deep
water borehole project in rural areas of Akwa Ibom State as ranging within
thirteen (13) days with an approximate cost of
four million,twelve thousand five hundred naira only (N4,012,500.00) as optimal construction
cost. To ensure easy compliance with this duration and cost range, critical
activities (jobs) that require close supervision/management attention during
the construction were also determined. This approach forms a guide against
costly technical mistakes. In addition, submersible pump equipped deep water borehole is recommended
as the best water supply source for Akwa Ibom rural communities due to its
reliability in all seasons and its water is safe and requires little or no
purification before use. The choice of submersible pump is to reduce the cost and to provide simple
technology for easy maintenance /operation which is within the reach of rural
dwellers. Also, the investigation was conducted and analyzed using network
modeling procedures. The optimal duration in hours for the different jobs
involved in this borehole construction including, site preparation/mobilization
of geophysical survey team.
DAVID, D (2023). Network Optimization Technique Of Borehole Water Supply Projects In Akwa Ibom State . Mouau.afribary.org: Retrieved Dec 22, 2024, from https://repository.mouau.edu.ng/work/view/network-optimization-technique-of-borehole-water-supply-projects-in-akwa-ibom-state-7-2
DAVID, DAVID. "Network Optimization Technique Of Borehole Water Supply Projects In Akwa Ibom State " Mouau.afribary.org. Mouau.afribary.org, 13 Feb. 2023, https://repository.mouau.edu.ng/work/view/network-optimization-technique-of-borehole-water-supply-projects-in-akwa-ibom-state-7-2. Accessed 22 Dec. 2024.
DAVID, DAVID. "Network Optimization Technique Of Borehole Water Supply Projects In Akwa Ibom State ". Mouau.afribary.org, Mouau.afribary.org, 13 Feb. 2023. Web. 22 Dec. 2024. < https://repository.mouau.edu.ng/work/view/network-optimization-technique-of-borehole-water-supply-projects-in-akwa-ibom-state-7-2 >.
DAVID, DAVID. "Network Optimization Technique Of Borehole Water Supply Projects In Akwa Ibom State " Mouau.afribary.org (2023). Accessed 22 Dec. 2024. https://repository.mouau.edu.ng/work/view/network-optimization-technique-of-borehole-water-supply-projects-in-akwa-ibom-state-7-2